Grep · sample report

Regulatory Check — You get a checklist of the licenses, permits, registrations, documents, taxes and rules your activity needs, with agency, cost, timeline and next steps.

workon demandoperational
Inputs used for this sample
Regulatory Check

Activity, product, project or buyer to map: Opening a coffee shop with outdoor seating and beer and wine sales

Jurisdiction or location: Austin, Texas, USA

What you already have (optional): LLC formed, EIN issued, lease signed, no sales tax permit yet

Austin Coffee Shop with Patio and Beer/Wine: 14 Permits Still Needed, Critical Path Is the City-Certified TABC Permit

Executive Summary

Read as: you are opening a coffee shop with outdoor seating and on-site beer and wine sales at a leased space in the City of Austin, Texas, with the LLC and EIN done and no sales tax permit yet. I assumed the site is inside Austin city limits and that the patio is on or next to the leased premises. Both assumptions are listed under open questions.

I count 14 items still needed (LLC and EIN are done), and the critical-path item is the TABC Wine and Malt Beverage Retailer's Permit (BG): it needs a City Clerk signature that only follows an Austin zoning review, and TABC says a new license can take 30 to 35 days from a complete application. The building-side chain (change of use, health plan review, certificate of occupancy, health permit) runs in parallel and decides your opening date.

This is not legal advice; confirm each item with the issuing agency. Fees below are the published amounts I found, with their dates. Where I found no current figure, the table says Unknown.

Checklist: what you need, by level

# Item Level Agency Rule / basis Needed when Fee Typical time Status Link
1 LLC formation State Secretary of State Not re-verified Done n/a n/a have n/a
2 EIN National IRS Not re-verified Done n/a n/a have n/a
3 Texas sales and use tax permit State Comptroller of Public Accounts Comptroller permit FAQ: required if you sell tangible personal property or taxable services Before first sale No fee, but a security bond may be required Unknown needed Permit FAQ
4 Unemployment tax account State Texas Workforce Commission TWC liability rules: register within ten days of becoming liable If you pay wages (liable at $1,500 gross wages in a quarter or one employee in 20 weeks) Unknown Unknown needed (if hiring) TWC liability page
5 TABC Wine and Malt Beverage Retailer's Permit (BG) Regulator Texas Alcoholic Beverage Commission BG authorizes wine and malt beverage sales for on- and off-premise consumption Before any alcohol is sold $903 listed for "all other counties" in TABC's Sept. 2021 fee notice; current fee not confirmed 30 to 35 days from a complete application needed TABC new licenses
6 City of Austin alcohol certification (City Clerk signature on TABC application) City Austin Development Services / City Clerk Certification follows an Austin zoning review After AIMS filing, before TABC issues New Zoning Review fees start Oct. 1, 2026; amount not stated on that page; a line "TABC Permission (TX Alcoholic Beverage Commission)" at $481.73 appears in the city's fee document, which I infer may be this fee (unconfirmed) Unknown needed Austin alcohol permits
7 Zoning and distance check for alcohol City Austin Development Services No sales within 300 feet of a church, school or public hospital; no on-site sales without a food and beverage certificate within 300 feet of a daycare Before signing off the TABC filing Included in item 6 Unknown needed Austin alcohol permits
8 Change of use / Certificate of Occupancy City Austin Development Services Change of Use may be needed to update the Certificate of Occupancy Before opening, if prior use differs Unknown Reviews cut from 11 disciplines to three on Oct. 1, 2025, typically about two weeks instead of two months needed (if use changes) Small business permitting
9 Commercial building permit (if you build out) City Austin Development Services Required to construct, alter or repair a building Before any buildout Unknown Unknown needed (if buildout) Commercial plan review
10 Food Enterprise plan review City Development Services, with Austin Public Health Required for new construction and remodels Before buildout Remodel under 2,500 sq ft $221; new construction $312 Unknown needed Fixed food establishments
11 Pre-opening health inspection City Austin Public Health Required for all new establishments; must pass before a permit issues After buildout, before opening $178 (FY2025-26 schedule) Unknown needed Fixed food establishments
12 Food Enterprise operating permit (annual) City Austin Public Health Issued after pre-opening approval; renew annually Before opening; renew annually $309 under $50,000 annual food sales, $618 for $50,000 to $149,999.99, $927 for $150,000 or more (FY2025-26) Unknown needed Fixed food establishments
13 Fire plan review and patio inspection City Austin Fire Department Fire Marshal's Office does plan review and fire inspections under the 2024 IFC with local amendments Before opening; patio before use Unknown Unknown needed Fire Marshal's Office
14 Patio authorization (only if patio is in a parking lot) City Development Services (Entertainment and Permitting Services), AFD Parking Lot Patio Permit: one-year term, balustrades or planters required if serving alcohol, no tents or permanent structures Before opening the patio Unknown (city says to ask staff) Unknown needed (if applicable) Parking Lot Patio Permit
15 TABC temporary modification of licensed premises Regulator TABC City recommends completing it before modifying a patio where alcohol is served Before building the patio, if alcohol is served there Unknown Unknown needed (if applicable) TABC licenses
16 Seller/server certification for staff Regulator TABC Strongly recommended, not stated as mandatory; may protect the employer under the Safe Harbor law Before staff sell beer or wine Unknown (school-set) About two hours online needed (recommended) TABC certification

The table has 16 rows, including the two completed items, which leaves 14 to do. Rows 9, 14 and 15 depend on facts I do not have (see open questions), so the real count may be lower.

KEY TAKEAWAY: The alcohol chain (items 5 to 7) and the building chain (items 8 to 13) are independent, and your opening date is whichever finishes last.

Order of operations

  1. Sales tax permit (item 3). It has no fee and no dependency beyond your existing EIN and LLC, so file it first.
  2. Confirm zoning and the 300-foot rule (item 7). Do this before spending on buildout, because a failed distance test blocks the alcohol permit. Austin's Land Use Assistance appointments are the city's route for zoning questions.
  3. Change of use and plan reviews (items 8, 9, 10, 13). Submit through Development Services. Health plan review is filed there for sites inside the city, per the health department page.
  4. TABC application in AIMS (item 5), then call the City Clerk (item 6). The city's process is: file in AIMS, then call the Clerk's office to start approval and signature. Item 6 depends on item 7.
  5. Patio steps (items 14, 15). Get TABC premises approval before building a patio where alcohol will be served.
  6. Buildout, then pre-opening health inspection and fire final inspection (items 11, 13), then operating permit (item 12) and certificate of occupancy. The health page says the pre-opening inspection is required to obtain a Certificate of Occupancy.
  7. Staff certification and unemployment tax account (items 16, 4) before the first shift.

Open questions and conditional triggers

Recent changes that affect timing and cost

Do next

  1. File the Comptroller sales tax permit application this week.
  2. Book a Land Use Assistance appointment to confirm zoning, the 300-foot test, and whether change of use is needed.
  3. Ask Entertainment and Permitting Services (512-974-2686, per the patio page) about the patio type and fees.
  4. Open your AIMS account and prepare the BG application, then call the City Clerk (512-974-2210) once it is filed.
  5. Confirm the current BG fee with TABC, because the only figure I found is from 2021.

Coverage note

I did not verify federal items (for example I-9 and federal payroll deposits), Texas franchise tax, local sales tax rates, the Austin sidewalk/right-of-way patio rules, signage, or the TABC fee chart's current amounts (the chart page links only to a PDF, and the one I could read is dated 2021). Health fees are from the FY2025-26 schedule; a FY2026-27 city schedule takes effect 1 October 2026 and I could not read its health-fee lines. Confirm each item with the issuing agency; this is not legal advice.